So after 4 days at PRG in Longbridge, the lighting and video prep is complete.

I’ve had the entire 10m x 6m Martin LC screen hanging in the warehouse to build the cable looms that will allow us to rig the screen in as short time as possible (so I can get back on the bus and get some sleep!). The control rack with processors for the LC and MiTRIX screens is built and wired.

I’ve experienced the typical video problems over the past couple of days; phantom flickers, shifted images, dodgy cables and connectors. After a few phone calls and some extra kit, we’re there.

All that remains to do now is install it all at Brixton on Thursday including building the MiTRIX screens to go along the risers, a job which could take a while while using a lot of cable ties and even more patience…

James